Construction Update

Points of Interest for the upcoming week:

1. Roofing to be started on Building One.
2. Continuing with masonry on Building One, which will include operations of heating generators throughout each night
3. Setting temporary rooftop heaters on Friday that does require a crane to lift them in place.
4. Waterproofing the deck along with any outside work on Building Two that is temperature sensitive.
5. Frame work in Building One and the garage will continue.
6. Siding at Building One will begin with installation.