Construction Update
Points of Interest for the upcoming week:
1. The construction site will be closed on Dec. 24th (Monday) and Dec. 25th (Tuesday). Workdays will be for the remaining days of the week: Dec. 26th, 27th, and 28th.
2. Snow removal will be ongoing.
3. Crane work for loading roofing is scheduled late in the week.
4. Deliveries will be kept at a minimum, although roofing deliveries will happen at the end of the week.
5. Window and door installation continues.
6. Wood and metal frame work continues.
7. Temporary heat generator will be utilized all week.
8. Masonry work along Heath Street will continue throughout the week.
1. The construction site will be closed on Dec. 24th (Monday) and Dec. 25th (Tuesday). Workdays will be for the remaining days of the week: Dec. 26th, 27th, and 28th.
2. Snow removal will be ongoing.
3. Crane work for loading roofing is scheduled late in the week.
4. Deliveries will be kept at a minimum, although roofing deliveries will happen at the end of the week.
5. Window and door installation continues.
6. Wood and metal frame work continues.
7. Temporary heat generator will be utilized all week.
8. Masonry work along Heath Street will continue throughout the week.